Using the
Global Project Planning (GPP) wizard, you can modify the properties of approved package sets at the package set level, such as shelf life and storage conditions, for the package sets associated with the PDSs selected in a project. The changes you make with the package set PDS project wizard are applied to all the approved package sets you select.
Note: The procedure below is a continuation of the
Update Product Detail Sets project in the
GPP wizard. The procedure presented in
Creating an Update Product Detail Set Project must be initiated first.
To modify package set details from the
Select Action page of the
GPP wizard:
-
Select
Modify Package Set on the
Select Action page.
-
Click
Next.
-
On the first
Modify Package Set page, select the product families containing products that have PDSs with the approved package sets that you want to update.
-
Click
Next.
-
On the second
Modify Package Set page, modify package set properties.
- To modify an attribute, click the check box next to the
attribute field and then specify a value. If you select a check box and leave the associated field blank, the package set property is updated with a blank value.
- Only the property attributes you check will be updated. The values for unchecked property attributes will remain unchanged in the package set you are updating.
-
Click
Next.
The
Perform another PDS Action page opens.
-
Do one of the following:
| Option
|
Action
|
| To return to the
Select Action page to select another update PDS action:
|
Click
Yes.
|
| To proceed to the
Summary page of the
GPP wizard:
|
Click
No.
|
-
Click
Next.
One of the following occurs:
- If you selected
Yes in step 7, the package set attributes are modified in the PDSs that you selected in step 3, and you return to the
Select Action page of the
GPP wizard.
- If you selected
No in step 7, the
Summary page opens. Go to step 9.
-
On the
Summary page, do one of the following:
| Option
|
Action
|
| To review the new project you created:
|
Select the project link on the
Summary page.
|
| To return to the view from which you invoked the
GPP wizard:
|
Click
Finish.
|
-
To view the project after you close the GPP wizard:
-
Click
Home.
-
Click
Projects.
-
Click the link for the project that you just created.
-
To view the details that GPP modified, navigate to the PDS.