When setting a due date and priority to an activity, the following condition apply:
- You must have
WRITE permissions on activities within the Entity Security section of Security Administration.
- The activities belong to a workflow which is not paused.
To set due date and priority for multiple activities:
-
Navigate to the list of activities using one of the following ways:
- Click
.
- Right-click on an assembly root, or a folder, or a leaf and select
View Activities List.
- Click
-
From the list of activities, select the activities for which you want to set due date and priority.
To find specific activities, use the Set Filter option.
-
Click
Mass Update.
-
Do the following:
- To schedule a due date, select Due Date and set a date using the
Calendar.
- To set priority, select Priority and select a number from the drop-down list.
-
Do the following:
- To overwrite the existing values and save, click
Update and Overwrite.
- To update changes when by default the fields do not have any values, click
Update and Preserve.