Use the Update Event Country Status Projected Dates Wizard
You can create or update projected dates for one or more event countries using the Update Event Country Status Projected Dates wizard.
Projected date planning is based on lead times set for each status. You select a pivot status, such as
Submitted or
Approved and enter a date for that status to enable the system to work forward, backward (or both) to calculate planned dates for other statuses.
Note: If the event was created from a timeline/event plan, you cannot calculate projected dates based on a status that was defined as an optional status in the timeline/event plan.
Only the event countries for which you have at least WRITE permissions are present for selection in the wizard. The wizard is only available if there is at least one unlocked event country schedule associated with the event. This wizard can only be used for events created from a timeline/event plan.
To use the
Update Event Country Status Projected Dates wizard: