You can calculate the projected dates in the event-country status schedule based on the project pivot status and project pivot status date for one or more events.
To calculate projected dates, you must have either a Submission Planning and Tracking or a Registration Planning and Tracking module license with at least
WRITE privileges,
WRITE privileges for the event entity, and
WRITE privileges for projects. Also, the events you select must have a status that maps to the project pivot status you select when completing the wizard.
To calculate projected dates for a project:
-
From the
Home page, click
Projects.
-
On the
Projects tab, click the project link.
The
Project Attributes page appears.
-
Click Event Country Dates to view a list of events associated with the project.
-
Click
Calculate Projected Dates.
The
Update Project Event Status Projected Dates wizard opens to the
Select Events page.
-
Select one or more events.
-
Click
Next.
The
Enter Project Pivot Dates page appears.
-
Do the following:
-
Specify a Project Pivot Status and a
Project Pivot Status Date.
-
Select a
Pivot Operation. See the topic
Calculating Projected Dates for an explanation of this attribute.
-
Click
Next.
A confirmation page opens, indicating the actions that will be taken.
-
Click
Next.
The
Summary page appears, confirming that the projected dates for the selected dates were updated.
-
Click
Finish.
Upon completion, the
Project Attributes page appears for the project you just updated. The
Project Pivot Status and
Project Pivot Status Date project attributes show the updated information you entered. On the
Events tab, click an event name link to navigate to the
Events Attributes page.
You can also open the
Event Attributes page by clicking the event code link on the
Event Country Dates tab. On the
Countries tab, click the country name link to view the event-country status schedule. The calculated projected dates appear in the event-country status schedule presented on the
Status Dates tab.